Project:   Rans - S-21 Outbound   -   VIEW REPORTS
Total Hours:1990
Total Flight Time:
Start/Last Date:Apr 03, 2021 - No Finish Date
Engine:Titan IO-340 180HP
Propeller:Whirlwind
 
Friendly URL: https://eaabuilderslog.org?s=RANS21RB

Home or Last Project Picture

Apr 01, 2024     Cowling, trim tab - (3 hours)       Category: Reassembly
Safety wired trim tab hinge pins (forgot to do this when I reattached the trim tab after painting). Attached trim motor actuator arm and cover. Fit cowling to check fit of air intake boot and how the baffle seals fit the underside of the top cowling. Also, checked clearance of inlet ramps to front baffling- all ok.


 